You will receive a 60-day and 30-day notice from ORSP as your award nears its end date. Your project administrator will also receive this notice and review your award’s financial position to determine what actions are necessary from a financial perspective.
Once you are within 3 months of your project end date, please coordinate with the appropriate post-award personnel to prepare final expenditures or to arrange an extension if a no-cost extension is appropriate.
While some time extensions do not require sponsor approval, most do require sponsor notification. In cases where an internal records need to modify the grant end date, an amendment approval form may be sufficient to resolve the extension approval.
Note that if an extension will not apply and a spend down plan is put in place, sponsors may not permit certain equipment or supply purchases. Please ensure that sponsor and program guidelines are followed. PI’s are responsible for completing any technical or final programmatic reports required by your sponsor. A copy of these reports should be forwarded to ORSP.